identify the major functional deliverables and subdividing those deliverables into smaller systems.



identify the major functional deliverables and subdividing those deliverables into smaller systems.

The company xxx (FROM THE ASSIGNMENT 1) decided to go on with Audio helping system.  The project team creates the  work breakdown structure by identifying the major functional deliverables and subdividing those deliverables into smaller systems. The team also performed Project Time management analysis (:Defined  Activities,  Sequenced Activities,  Estimated Activity Resources, and  Estimated Activity Duration

 

The result of their work is presented in the Table 1.

 

Table 1

Acivity Abreviation Duration in Days Predecessor
Recording

 

Spectaral analysis and calculation

Technical Requirements

Contacting suppliers

Board design

Algorithm development

Embedded system

Testing

A

 

B

C

D

E

F

G

H

30

 

60

15

15

20

90

90

10

 

 

A

B

C

C

B

F, D, E

G

       

 

TASK 1 (16 marks)

Develop Project Schedule network:

  • Draw Network Diagram
  • Determine Critical path
  • Forward Pass Calculation (Early Start, Early Finish)
  • Backward Pass Calculation (Late Start, Late Finish)
  • Slack (Float) Calculation.

The calculations have to be commented using at least 3-5 sentences for explanation, and scenarios.

 

 

 

TASK 2 (16 marks)

Table 2. SCHEDULE AND COST PERFORMANCE BASELINE

Acivity Abreviation Duration in Days Allocated cost of project [$]  
Recording

 

Analysis and calculation

Technical Requirements

Contacting suppliers

Board design

Algorithm development

Embedded system

Testing

A

 

B

C

D

E

F

G

H

30

 

60

15

15

20

90

90

10

4000

 

12000

3000

2000

5000

18000

18000

2000

Recorder+ one person

 

2 engineers

1 engineer

1 admin

1 engineers

2  engineers

2 engineers

1 tester

 

  • Using previously done Project Time management analysis, Estimate planed start and finishing date for each activity along the critical path.
  • Project management team decided that for the Performance report it is the best to choose the day when the Embedded system programing is completed. After analysis the project management team was found that only 75% of the work on the Embedded system is done and $16500 are spend.
  • Draw Actual Performance table
  • Calculate Cost Variance (CV) , Shedule variance (SV), Cost Performance Index (CPI) and Shedule performance Index (SPI)
  • Analyse situation and possible scenarios.
  • Perform Forecast analysis by calculating: Budget at completion (BAS); Estimate at Completion (EAS); Estimate to complete (ETC) and Variance at Completion(VAC)
  • Calculate “To Complete Performance Index” and give a comment

 

TASK 3 (8 marks)

Comment what has to be done for Quality control. And what will be the best Metrics.


Price: £ 99

100% Plagiarism Free & Custom Written, Tailored to your instructions

Details

  • Title: identify the major functional deliverables and subdividing those deliverables into smaller systems.
  • Price: £ 99
  • Post Date: 2021-04-13T09:18:55+00:00
  • Category: Research Paper Queries
  • No Plagiarism Guarantee
  • 100% Custom Written

Customer Reviews

John P.

The rates are a bit expensive for me of the essay writing service but the overall look is amazing. The references and formatting are done beautifully. So, I feel that the high rates are worth all these qualities. I want to thank you for great help.

United Arab Erimates    2020-03-12

Carl

I am not good at designing PowerPoint presentations so I took help from Insta Research. The format is cool and attractive. All the information is nicely placed and used. I am looking forward to presenting so that I could demonstrate my presentation and receive good comments. Thank you for help.

United Kingdom    2020-03-12

Write your Feedback

Your email address will not be published. Required fields are marked *