[Solved] CREATE A TIME PHASED BUDGET FOR YOUR EXAMPLE PROJECT USING BOTTOM UP ESTIMATING

  100% Pass and No Plagiarism Guaranteed

[Solved] CREATE A TIME PHASED BUDGET FOR YOUR EXAMPLE PROJECT USING BOTTOM UP ESTIMATING

In this paper, you are to create a time phased budget for your example project using bottom-up estimating. Furthermore, provide a risk register and quality management plan. Finally, present closure checklist and project evaluation.
  1. Gantt chart-Take the WBS you have already developed. Define all of the activities that will be necessary to create each deliverable in your WBS. Create a schedule for your project. First create the schedule by hand using Post-itNotes, and then put the information into MS Project. Take screenshots of the schedule to be pasted in your word document that you are submitting. Be sure to include all of the summary rows (including the first row for the project title) and any key milestones. Make sure the critical path is easy to see. (Screenshot only)
  2. Create a time-phased budget for your example project using bottom-up estimating. To the extent your sponsor will supply rates for workers, use those. Approximate rates for ones you cannot get. Ask your sponsor how they treat indirect costs. Be sure to include direct labour costs for you and your team mates and add 20% for fringe. State all assumptions and constraints you have used when creating your budget. State how confident you are in your estimates and what would make you more confident. Give examples of known knowns and known unknowns on your project. Tell how you have budgeted for both of them plus how you have budgeted for unknown unknowns.
  3. Create a risk register ( 4 risks- 3 negative and 1 positive risk)for your example project.
  4. Quality Management Plan. It should include:
    A short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client. ( 4 marks)
    Develop and describe 3 quality issues related to this project that your project team could implement to ensure quality ( 6 marks)
  5. Closure checklist and project evaluation. 
    Develop a closure checklist that the project team will use to ensure that the project has been closed properly.
    Develop a project evaluation –outline and discuss how your project’s MOV will be evaluated.

 

 

Below are the Content of the WBS:

 

Social media Web Application Development

  1. Application Development

1.1Create Code Design Document

1.1.1. Define Features Included in Each Release

            1.2. Implement Code Control System

            1.3. Setup Development Environment

            1.4. Database Model

                        1.4.1. Design Database Schema

                        1.4.2. Create Database

                        1.4.3. Design DB Schema Document

            1.2. GUI Development

                        1.2.1. Frontend Design

                                                1.2.1.1. Set up Working Environment

                                                1.2.1.2. Adopt Theories

                                                1.2.1.3. Select Appropriate Programming Language

                                                1.2.1.4. Host the Website

 

                        1.2.2. Backend Design

                                                1.2.2.1. Data Input and Manipulation

                                                1.2.2.2. Technology Set Up

                                                1.2.2.3. Component Generation

                                                1.2.2.4. Output Documentation

 

            1.3. Code Generation

                        1.3.1. Release Testing

                        1.3.2. Bug Fixes

  1. Application Testing

     2.1. Test Environment Setup

     2.2. Test Plan

     2.3. Unit Testing

     2.4. Results reporting

  1. Application Deployment

     3.1. Production Data Migration

     3.2. Operations Switch Over

     3.3. Documentation

     3.4. End User Documentation

     3.5. Application Administration Documentation

     3.6. Disaster Recovery

  1. Training

     4.1. End User Training

     4.2. System Administrator Training

 

 

100% Plagiarism Free & Custom Written,
Tailored to your instructions


International House, 12 Constance Street, London, United Kingdom,
E16 2DQ

UK Registered Company # 11483120


100% Pass Guarantee

STILL NOT CONVINCED?

View our samples written by our professional writers to let you comprehend how your work is going to look like. We have categorised this into 3 categories with a few different subject domains

View Our Samples

We offer a £ 2999

If your assignment is plagiarised, we will give you £ 2999 in compensation

Recent Updates

Details

  • Title: [Solved] CREATE A TIME PHASED BUDGET FOR YOUR EXAMPLE PROJECT USING BOTTOM UP ESTIMATING
  • Price: £ 99
  • Post Date: 2021-10-25T04:59:36+00:00
  • Category: Assignment Queries
  • No Plagiarism Guarantee
  • 100% Custom Written

Customer Reviews

[Solved] CREATE A TIME PHASED BUDGET FOR YOUR EXAMPLE PROJECT USING BOTTOM UP ESTIMATING [Solved] CREATE A TIME PHASED BUDGET FOR YOUR EXAMPLE PROJECT USING BOTTOM UP ESTIMATING
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

I have been taking help from Insta Research since 2015 and believe me, this place is incredible in giving the best help in assignments and essays. I also ask them to run plagiarism in my essays that I have written, and they always gave me accurate results. I am literally blessed to have a strong bonding with this site so that in any need of urgency, I contact them and find them always beside me. Thank you!
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

Writing is not my field. I take help from this website for my accounting assignment. The work is good and I scored good grades in it. Thank you from the bottom of my heart.