Question 3.
|
Question :
|
(TCO F) The following data were obtained from an information systems project to upgrade and expand a local area network. Activity Duration Predecessors Task Budget A 3 days
— $4,920 B 6 days — $7,680 C 3 days A $15,140 D 2 days
B $3,980 E 3 days B $5,630 F 2 days C and D $2,270
At the end of Day 7, the status of the project is as follows. Activity % Complete Actual Cost A 100% $4,200 B 100% $8,740 C 100% $18,250 D 65% $2,600 E 10% $560 F 0% $0
(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E. (b) As project manager, write a brief summary of the status of the project at this time.
|