We're Open
+44 7340 9595 39
+44 20 3239 6980

[Solved]find (a) the crash cost per day per activity; (b) which activities should be crashed to meet a project deadline of 12 days

100% Plagiarism-Free Work & Confidential Service

[Solved]find (a) the crash cost per day per activity; (b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and (c) what the extra cost is to crash the project.

Using the network below and the
additional information provided, find
(a) the crash cost per day per activity;
(b) which activities should be crashed to meet a project deadline of 12
days at minimum cost; and
(c) what the extra cost is to crash the project.

Activity

Normal
Time

Crash
Time

Normal
Cost

Crash
Cost

A

5

3

$300

$600

B

3

2

$250

$450

C

6

4

$400

$500

D

5

3

$150

$400

A.

Question 2.

Question :

(TCO E) The following information is
extracted from a project to develop a state-of-the-art alternative power
energy storage device.
Activity Duration Predecessors Resources
A 4 days
—
1 research
engineer
B 3
days
A 1 test
engineer
C 5
days
A 1 design
engineer
D 2 days
A
1 marketing
specialist
E 3
days
B 1 prototype
builder
F 4
days
D 1 test
engineer

The owner has stipulated that in order to provide continuity throughout
the project, the same individual must handle all activities under his or
her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the
activities involved, the time frame of the conflict(s), which resources
are involved, and the quantity required.
(b) Given the owner’s stipulation regarding project continuity and the
need to minimize project duration, how can this conflict be resolved?
What will be the effect on the project duration?

Question 3.

Question :

(TCO F) The following data were obtained from
an information systems project to upgrade and expand a local area
network.
Activity Duration Predecessors Task Budget
A 3 days

— $4,920
B 6 days
—
$7,680
C 3
days
A
$15,140
D 2 days

B
$3,980
E 3
days
B
$5,630
F 2
days
C and D $2,270

At the end of Day 7, the status of the project is as follows.
Activity % Complete Actual Cost
A
100%
$4,200
B
100%
$8,740
C
100% $18,250
D
65%
$2,600
E
10%
$560
F
0%
$0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B,
C, D, and E.
(b) As project manager, write a brief summary of the status of the
project at this time.

Question 4.

Question :

(TCO B) You are project manager for three
different projects.

Project A: This project is behind schedule by 12 weeks. It was to have
been completed in 3 months. The sponsor has additional funds to help
complete the project on time if needed but does not want to increase risk
to the project.
Project B: This project is scheduled to take 28 weeks to complete. You
are in the planning stage of the project. You need to reduce the schedule
for this project by 9 weeks. This project has a number of predecessors
that were created by the project team’s preference. The sponsor insists
on having all the work done on time without unduly increasing risk or
costs to the project.
Project C: This project is in the execution stage of the project. It is
behind schedule by 8 weeks; it was scheduled to be completed in 10 weeks.
The sponsor is desperate to accomplish something on this project. The
budget is limited to the original amount, and all soft predecessors have
already been removed.

For each of the project above, choose an appropriate schedule compression
technique. Explain your choice.

 
 

Points Received:

20 of 20

 

Comments:

 

Question 5.

Question :

(TCO F) Given the following information,
calculate the CV, SV, CPI, and SPI for this project. Also provide
recommendations to improve the project’s performance if needed.

Activity A: This activity is 60% complete, at a cost of $80,000. It is at
the end of Week 5 of 8 and was projected to cost 200,000.

Activity B: This activity is not started yet; it will start in 2 weeks.
It is planned to cost $400,000. Its costs to date are $0.

Activity C: This activity is complete. It was completed in 6 weeks; it
was supposed to have been completed in 5 weeks. The original budget for
this activity was $400,000; in the end, it cost $450,000.

Activity D: This activity is 75% complete with an original budget of
$200,000. Costs to date are $65,000, and the project is at the beginning
of Week 3 of 4.

Need a Fresh, Custom-Written Answer?

Get professionally prepared work tailored to your requirements.

Original content • Confidential service • Tailored to your instructions

Details

  • Title: [Solved]find (a) the crash cost per day per activity; (b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and (c) what the extra cost is to crash the project.
  • Price: £ 110
  • Post Date: Fri, 03 Jan 2025 18:41:29 +0000
  • Category: Assignment
  • No Plagiarism Guarantee
  • 100% Custom Written

Customer Reviews

[Solved]find (a) the crash cost per day per activity; (b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and (c) what the extra cost is to crash the project. [Solved]find (a) the crash cost per day per activity; (b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and (c) what the extra cost is to crash the project.
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

Insta Research is a very helpful place to buy a resume in the first place. I gave them my details and did not expect that they would come up with such an exclusive design. My personality is professionally enhanced through the resume made by them. I am thankful for the depth of my heart as I would have never approached that level of excellence in my resume. Wish you good luck ahead and again thank you!
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

I received my order last night and now I’m writing my reviews. My assignment has all the points I needed along with a good style. The citations used are relatable and professional. The best thing is the discount I got because I recommended my friend too to use their service. I am so pleased to use this effective service. The features are also amazing, everything is good. Will come again soon!