a) List and explain very briefly the FOUR main criteria for assessing the success of a project.

  100% Pass and No Plagiarism Guaranteed

a) List and explain very briefly the FOUR main criteria for assessing the success of a project.

BCS Level 5 Diploma in IT IT PROJECT MANAGEMENT
Section A
Answer Section A questions
A1
a) List and explain very briefly the FOUR main criteria for assessing the success of a project.
(4 marks)
b) As a project manager you will normally receive several different types of reports and other recorded information to help you control
the progress of a project. Your project is falling behind schedule and you need to identify the main reason for this delay. Explain which 
reports, or other information, you might use to identify each of the following possible reasons:
i) staff who are intended to be working full-time on the project are taken off sometimes to help resolve emergency situations on other
projects;
ii) the original estimates of development times were too low
iii) the project scope has been extended to meet additional requests from users
iv) staff productivity is lower than expected.
(8 marks)
c) Identify FOUR different options that are available for bringing such a project back on schedule when it has been found to be running
late. Explain the cost implications of each of these options.
(13 marks)
A2 Your company has decided that it needs a new sales recording system and that an off-the-shelf package is the best solution.
The main tasks have been identified and durations assessed as follows:
 B cannot start until A is completed
 C, E, H and I cannot start until B is completed
 D cannot start until C is completed
 F cannot start until E is completed
 G cannot start until D is completed
 J cannot start until F, G and I are completed
 K cannot start until H is completed
 L cannot start until J and K are completed
 M cannot start until L is completed
a) Draw an activity-on-node diagram for these 13 project tasks (A to M). Calculate, display and clearly label on the diagram, the
earliest and latest start and finish times and float of each task
(11 marks)
b) Describe how each of the following changes to task durations (on their own) would affect the critical path and project duration.
i) Task B - reduced to 1 week
ii) Task F - increased to 11 weeks
iii) Task G - reduced to 7 weeks
(8 marks)
c) Identify THREE items of information regarding the planning and progress of a project that are not shown on an Activity Network
but could be displayed on a Gantt Chart.
(6 marks)
A
Draw up a functional requirements specification
4 weeks
B
Consider various relevant software packages and select one
3 weeks
C
Identify and specify the necessary hardware and communications equipment
2 weeks
D
Order the hardware and equipment
1 week
E
Identify the key package modifications needed to meet the functionality required
2 weeks
F
Modify the software package as necessary
8 weeks
G
Accept delivery and install all hardware and equipment needed for the package
10 weeks
H
Design a training plan
3 weeks
I
Set up a testing plan
3 weeks
J
Unit test all the amended package modules
4 weeks
K
Train the users
3 weeks
L
Full integration and acceptance testing
3 weeks
M
Implement the new system
1 week
A3
a) Describe FIVE techniques a project manager could use to identify risks. (10 marks)
b) Explain the difference between a project risk and a business risk. (4 marks)
c) Describe FIVE different tactics for managing a project risk. (11 marks)
Section B
Answer Section B questions in Answer Book B
B4
a) With the aid of suitable diagrams briefly explain
i) Incremental building, (8 marks)
ii) Iterative development. (8 marks)
b) Prototypes can used in iterative agile development. Outline the advantages and disadvantages of using prototypes. (9 marks)
B5
a) The Capability Maturity Model Integrated (CMMI) can be used to assess the level of process maturity for an organisation.
With reference to CMMI:

i) draw and label a diagram showing the five maturity levels, (5 marks)
ii) for EACH of the FIVE CMMI levels, outline the typical practices you would expect to find. (10 marks)
b) Quality management systems such as ISO9001 are concerned with the quality of organisational process. Critically evaluate up to
 FIVE features of ISO9001. (10 marks)
B6
a) It is possible to categorise the power and interest of a project stakeholder using a 2x2 matrix diagram.
i) Sketch a suitable 2x2 matrix and label each category. (4 marks)
ii) For EACH of the FOUR categories of stakeholder that you can identify outline a suitable management approach that you might
take. (12 marks)
b) A project manager needs to effectively deal with customer expectations. Describe any THREE steps you can use in managing
expectations (9 marks)

100% Plagiarism Free & Custom Written,
Tailored to your instructions


International House, 12 Constance Street, London, United Kingdom,
E16 2DQ

UK Registered Company # 11483120


100% Pass Guarantee

STILL NOT CONVINCED?

View our samples written by our professional writers to let you comprehend how your work is going to look like. We have categorised this into 3 categories with a few different subject domains

View Our Samples

We offer a £ 2999

If your assignment is plagiarised, we will give you £ 2999 in compensation

Recent Updates

Details

  • Title: a) List and explain very briefly the FOUR main criteria for assessing the success of a project.
  • Price: £ 149
  • Post Date: 2024-08-28T18:23:38+00:00
  • Category: Assignment
  • No Plagiarism Guarantee
  • 100% Custom Written

Customer Reviews

a) List and explain very briefly the FOUR main criteria for assessing the success of a project. a) List and explain very briefly the FOUR main criteria for assessing the success of a project.
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

This is my second order which I booked recently at Insta Research. I just got my coursework completed expertly. Just waiting for good scores now.
Reviews: 5

A masterpiece of assignment by , written on 2020-03-12

My order went 3 hours late and I also went mad. Then the customer support team calmed me down and offered me a flat discount of 50%. However, I did get my order and chilled out as the work was exactly what I requested. Next time I would place my order a bit sooner to save any trouble.